April Endgame · Issue #25250 · microsoft/vscode · GitHub
Skip to content

April Endgame #25250

Description

@mjbvz

Endgame Schedule

  • April 25, Code freeze for the endgame
  • May 5, Endgame done

Tuesday, April 25

  • Code freeze at 5pm PT
  • Ensure we have a green build on all platforms
  • All test items contain sufficiently comprehensive test descriptions by 6pm PT

Wednesday, April 26

  • Test plan items assigned
  • All closed feature-requests either have a verification-needed or on-testplan tag
  • Testing
  • Verification needed
  • Testing
  • Remind team members to assign issues that they intend to fix to the April milestone
  • Fixing (self-assigned, milestone assigned)
  • Verification

Thursday, April 27

  • Fixing last issues
  • Verification
  • Run OSS tool after merging shrink-wrap findings endgame master
    • The LCA review of the ThirdPartyNotices.txt files is not needed anymore
  • Check new OSS usage is entered into the OSS registry endgame master

Friday, April 28

Friday/Monday
  • Freeze insider builds – endgame master
  • Branch code to release/<x.y> and release masterendgame master
  • Bump up the version in package.jsonendgame master
  • Announce master is open for business endgame master
  • Polish release notes redmond
Monday – Wednesday

Note: The Insiders build needs to be in the wild for 24 hours before we can enter the last phase of the endgame.

Thursday/Friday

Metadata

Metadata

Labels

endgame-planVS Code – Next release plan for endgame

Type

No type

Projects

No projects

Milestone

Relationships

None yet

Development

No branches or pull requests